Milestone: Awbrey Park 4th Grade (90) deployed on 2/13
Milestone: Awbrey Park 5th Grade (90) deployed on 2/22
Milestone: Spring Creek 4th and 5th Grade (120) deployed Monday, 3/4
Milestone: Madison 6th Grade (178) deployed Monday, 3/11 (official rollout 3/20)
Sheldon HS Science (160) deployed Monday, 4/1
Monroe Science (80) deployed week of April 8th
Cal Young Science (40) deployed week of April 15th
North Region
iPads – Ordered and received
iPads Inventoried – Completed
iPad Carts – Ordered (Note: We ran into some major problems getting these ordered. Recommend ordering a month in advance for future purchases and delivering directly to school)
iPad Cart Supplies – Labeler, Labeling tape, keychains
iPad Cases – Ordered; first batch received 1/28 additional units received 1/29
List of Apps from Teachers – List compilation received 1/29 (Still receiving app lists piecemeal). Setting a priority to improve the app vetting process. We will be working on a new process with Peter/Kim.
Carts assigned to schools – Completed, delivered 2/13. Some cart movement remains for Spring Creek.
iPads assigned to carts – In progress
MDM Management Solution evaluated – In progress, using Meraki for beginning phases if all goes well (Corvallis visit 1/28)
Imaging of iPads – Configurator, iTunes – In progress
Sync Station Setup – In progress. Completed for Awbrey Park 2/22.
Sheldon Region
iPad carts ordered and received
iPad Minis ordered and received – inventory in process
iPad Mini cases ordered and received