Milestone: Awbrey Park 4th Grade (90) deployed on 2/13

Milestone: Awbrey Park 5th Grade (90) deployed on 2/22

Milestone: Spring Creek 4th and 5th Grade (120) deployed Monday, 3/4

Milestone: Madison 6th Grade (178) deployed Monday, 3/11 (official rollout 3/20)

Sheldon HS Science (160) deployed Monday, 4/1

Monroe Science (80) deployed week of April 8th

Cal Young Science (40) deployed week of April 15th

 

North Region

iPads – Ordered and received

iPads Inventoried – Completed

iPad Carts – Ordered (Note: We ran into some major problems getting these ordered. Recommend ordering a month in advance for future purchases and delivering directly to school)

iPad Cart Supplies – Labeler, Labeling tape, keychains

iPad Cases – Ordered; first batch received 1/28 additional units received 1/29

List of Apps from Teachers – List compilation received 1/29 (Still receiving app lists piecemeal). Setting a priority to improve the app vetting process. We will be working on a new process with Peter/Kim.

Carts assigned to schools – Completed, delivered 2/13. Some cart movement remains for Spring Creek.

iPads assigned to carts – In progress

MDM Management Solution evaluated – In progress, using Meraki for beginning phases if all goes well (Corvallis visit 1/28)

Imaging of iPads – Configurator, iTunes – In progress

Sync Station Setup – In progress. Completed for Awbrey Park 2/22.

 

Sheldon Region

iPad carts ordered and received

iPad Minis ordered and received – inventory in process

iPad Mini cases ordered and received